Amazon Web Services celebrated the groundbreaking of a new data center in Jasper County, Northwest Indiana. The ceremony took place on the outskirts of Wheatfield, featuring speeches from Amazon leaders, local officials, and partners. The facility, named Project Rise, will be powered by NIPSCO’s adjacent R.M. Schahfer generating plant.
The data center is set on 320 acres purchased from NIPSCO. The construction begins amidst significant investment: $7 billion for the center and projected savings of $1.25 billion for NIPSCO customers over 15 years. The project promises 250 permanent local jobs.
Amazon and Ryan Companies announced $150,000 in grants to local organizations, including $20,000 to Sorrowful Mother Church Food Pantry, with an additional $10,000 from NIPSCO. Jasper County Council member Jacob Misch highlighted Amazon’s contributions of nearly $329 million to the county in the first decade, aiding fire departments, law enforcement, and emergency services.
Jasper County Board of Commissioners president, Rein Bontreger, emphasized the financial benefits, despite the center being outside Wheatfield town limits. Wheatfield Town Council member Dean Stalbaum acknowledged mixed feelings but appreciated Amazon’s $25 million investment in expanding domestic water services and a $25 million bond payment.
To facilitate the project, Jasper County approved a 10-year property tax abatement and a 35-year exemption on enterprise information technology equipment. This inclusion brings over $700 million in community impact payments over 35 years.
Svetlana Anikeeva, Amazon’s director of data center delivery, underscored community relations and responsible development as key priorities. Amazon also pledged to restore 425 acres of the Kankakee River watershed habitat with Shirley Heinze Land Trust, enhancing water availability by over 110 million gallons yearly.
The data center plans to optimize its environmental profile by using outside air cooling for 98% of the year. Water-based cooling technology will activate during peak heat, designed to be 80% more water-efficient than the industry standard. This reduces electricity demand by up to 35% during peak loads, with Amazon funding the necessary water and sewer infrastructure to support the center.
Jim Masters, a freelance reporter, provides this coverage for the Post-Tribune.