Texas’ data-center industry is expanding rapidly. This growth may negatively impact efforts to reduce air pollution that have been underway for decades. Research highlights the potential consequences of the increased electricity demand brought on by the surge in artificial intelligence. The study, conducted by the Houston Advanced Research Center (HARC), evaluates scenarios for supplying electricity to these data centers and their impact on emissions.
HARC’s analysis models the effects of increased electricity generation on emissions of nitrogen oxides (NOx), volatile organic compounds (VOCs), sulfur dioxide, fine particulate matter (PM2.5), and carbon dioxide through the year 2031. The researchers emphasize that the method of electricity generation plays a crucial role in determining the environmental impact. HARC has been contacted for further comment.
Data centers are proliferating across Texas, with ongoing projects in areas such as Abilene, the Dallas-Fort Worth area, San Antonio, Austin, and West Texas. The Texas comptroller tracks qualifying data centers and large data-center projects linked to major companies like Google, Microsoft, Amazon, and Oracle.
The City of Abilene provides information on data-center construction, including the Stargate project. Fort Worth reported in June the presence of four data centers, comprising 10 buildings and roughly 3 million square feet, with more projects proposed nearby.
Impact on Emissions Progress
Texas has reduced its emissions notably over the past two decades. From 2002 to 2024, NOx emissions from power generation dropped 67 percent, sulfur dioxide fell by 80 percent, VOCs decreased by 37 percent, carbon dioxide was cut by 52 percent, and PM2.5 diminished by 60 percent.
Electricity demand from data centers threatens this trajectory. In one HARC scenario where demand is met by the Texas electricity grid, NOx emissions in 2031 could surge by 136 percent compared to projections without additional data center demand. This would approach levels last recorded in 2004. VOC emissions could rise by 32 percent compared to 2002, and PM2.5 emissions might reach their 2006 volume.
Power sources significantly affect emissions. If data centers rely solely on fuel-burning to generate electricity, nitrogen oxide emissions may be two to ten times higher compared to using a mix of grid electricity, solar, and wind energy. Even the scenario with the cleanest energy sources indicates that data-center growth would increase emissions due to the substantial electricity requirements.
Surge in Data Center Demand
Figures from the Electric Reliability Council of Texas (ERCOT) demonstrate the scale of data-center development potential. In August, Governor Greg Abbott noted ERCOT was processing requests for over 474 gigawatts to connect to the grid, with nearly 90 percent originating from data centers. Abbott called for an audit of data-center projects covering electricity and water needs, as well as on-site generation plans.
In September, Abbott instructed the Texas Commission on Environmental Quality (TCEQ) to stop permitting for data centers until the ERCOT audit was complete, citing concerns about grid reliability and natural resources. TCEQ has been contacted for comment.
HARC indicates that Texas’ future emissions hinge on current power supply decisions, warning that the planned data-center expansion could lead to varying impacts, from marginal increases in emissions to a reversal of past environmental progress.